Source: Steelman ERP CRM Project Plan v1, 23 Sep 2026 (draft for baselining). Dates, owners and thresholds are proposals, not commitments. People get named at G1.
</aside>
<aside> ✅
Verified locally
DB + model · workflow UI · 31 tests · demo migration · Bicep compiles
</aside>
<aside> ⏳
Not yet verified
Azure · Linux image · Entra sign-in · MYOB/Excel · real data
</aside>
Switch views for Timeline, Status board, By workstream, Gates and Progress. Update statuses here as work moves.
<aside> 🏁
G1 · 2 Oct
Scope baseline
Owners, costs, scope, source inventory
</aside>
<aside> 🧪
G4 · 13 Nov
User acceptance
Mandatory scenarios pass; critical defects closed
</aside>
<aside> ☁️
G2 · 16 Oct
Staging ready
Entra, Blob and PostgreSQL verified; MYOB/Excel decision
</aside>
<aside> 🟢
G5 · 20 Nov
Go-live decision
Rehearsal, recovery proof, training
</aside>
<aside> 📦
G3 · 30 Oct
Release candidate
Priority fixes; migration rehearsal reconciled
</aside>
<aside> 🤝
G6 · 4 Dec
Operational handover
Support accepts ownership
</aside>
Critical path: decisions → source mapping + fixes → deployed RC → UAT + rehearsal → recovery + cutover approval → launch.
Workflows
Every mandatory scenario passes with SME evidence, including variations, revised drawings, partial receipts, failed QA, mixed-project nesting and partial delivery/invoicing.
Data
100% of in-scope records imported or on an approved exception list. No orphan links. Quantity and financial totals reconcile to source. Every attachment opens and matches its hash.
Security
All 7 roles tested with real Entra accounts. Unauthorised users can't reach restricted values, files or audit. No open critical/high issues.
Quality
No open Sev 1/2 defects. p95 common screen load ≤3 s at agreed volume and concurrency.
Recovery
DB + Blob restore demonstrated to a coherent point. Alerting, support ownership, incident contacts and user guides verified.