Steel-fabrication workshop planner + CRM/ERP: enquiry β quote β job β estimating β procurement β workshop β QA β delivery β invoice. Built on native PostgreSQL 16, Express 5, React 19 and Azure.
</aside>
<aside> π§±
63
domain tables
</aside>
<aside> π₯
7
app roles
</aside>
<aside> β
31 / 31
tests passing
</aside>
<aside> π
23 Nov
launch target
</aside>
<aside> π¦
Where we are (25 Sep 2026): v0.2.0 is built and verified locally only. The stakeholder review supported the consultantβs recommendation to pursue the custom PostgreSQL/Azure ERP rather than Smartsheet; the business go/no-go remains open. Next up is Phase 1, Confirm scope (28 Sep β 2 Oct), ending at gate G1. Azure staging, real Entra sign-in, real-data migration and MYOB go-live are still ahead. [1]
</aside>
<aside> β
Recommendation
Proceed toward a custom PostgreSQL application on Azure. The review found 8 of 14 Phase 1 requirements blocked in Smartsheet, including relational integrity, many-to-many traceability and financial-data security. [1]
</aside>
<aside> π³
Operating estimate
Approximately $400/month for production Azure infrastructure plus about $80/month for stagingβup to roughly $500/month in total. [1]
</aside>
Follow-ups
Source: β£

Steelman ERP: weekly workshop plan (demo data)
Diagrams, API layers, design rules, migrations, access
Setup, commands, repo map, env vars, conventions
Target infra, deploy steps, acceptance checklist, rollback
Importer, MYOB, Excel workbook, QuoteFlow
Phases, gates, risks, decisions, live Task Register
Platform limits found in the Aug 2026 build
Mockups of every module, desktop and mobile
gantt
title Steelman ERP / CRM rollout (2026)
dateFormat YYYY-MM-DD
axisFormat %d %b
section Build
v0.2.0 verified locally :done, b1, 2026-09-23, 3d
section Scope and design
1 Confirm scope :active, p1, 2026-09-28, 2026-10-02
2 Validate design : p2, 2026-10-05, 2026-10-09
section Build-out
3 Prepare staging : p3, 2026-10-05, 2026-10-16
4 Complete release work : p4, 2026-10-12, 2026-10-30
section Acceptance
5 Accept with users : p5, 2026-11-02, 2026-11-13
6 Rehearse launch : p6, 2026-11-16, 2026-11-20
section Go live
7 Launch and support :crit, p7, 2026-11-23, 2026-12-04
<aside> π
G1 Scope baseline Β· 2 Oct
</aside>
<aside> βοΈ
G2 Staging ready Β· 16 Oct
</aside>
<aside> π¦
G3 Release candidate Β· 30 Oct
</aside>
<aside> π§ͺ
G4 User acceptance Β· 13 Nov
</aside>
<aside> π’
G5 Go-live decision Β· 20 Nov
</aside>
<aside> π€
G6 Handover Β· 4 Dec